Correct Answer:
A. 39
The correct answer is 39. This is an inverse proportion problem. The total amount of work is constant. If 18 workers finish a job in 26 days, the total work units are 18 workers * 26 days = 468 work units. To finish the same 468 work units in 12 days, we need to find the number of workers (x).
- The equation is x * 12 days = 468 work units.
- Solving for x: x = 468 / 12 = 39 workers.
- Options 36, 30, and 42 are incorrect calculations that do not maintain the constant total work.