Ad
Sponsored by Sir Tauqeer
CLICK HERE TO JOIN SIR TAUQUEER WHATSAPP GROUP
FOR PREPARATION CLASSES AND JOBS UPDATES
Join Now

If 18 workers finish a job in 26 days, how many workers are needed to finish it in 12 days?

A. 39
B. 36
C. 30
D. 42
Correct Answer: A. 39

The correct answer is 39. This is an inverse proportion problem. The total amount of work is constant. If 18 workers finish a job in 26 days, the total work units are 18 workers * 26 days = 468 work units. To finish the same 468 work units in 12 days, we need to find the number of workers (x).

  • The equation is x * 12 days = 468 work units.
  • Solving for x: x = 468 / 12 = 39 workers.
  • Options 36, 30, and 42 are incorrect calculations that do not maintain the constant total work.

Leave a Comment

Join Our WhatsApp Channel ×
Scroll to Top