In a project network, an activity on the critical path has zero float and is delayed by three days. If no corrective action is taken, what is the expected effect?
A.The project completion date moves three days later.
B.A non-critical activity automatically absorbs the delay.
C.Project duration remains unchanged because float is shared.
D.Only the project budget changes, not its completion date.
Correct answer is:
A. The project completion date moves three days later.