This is a classic work and time problem, which relies on the concept of total work units. First, calculate the total work required: 4 men working for 42 days equals 4 * 42 = 168 man-days of work. Next, determine the effective workforce under the new conditions. If three men work full days and one man works half days, the effective number of men is 3 + 0.5 = 3.5 men.
- To find the time taken, divide the total work by the effective workforce: 168 man-days / 3.5 men = 48 days (B).
- Options 45 days (A), 52 days (C), and 60 days (D) are incorrect calculations that do not account for the reduced work output of one man.
Is this answer helpful and correct?
0 agree0 disagree