Correct Answer:
A. The project completion date moves three days later.
Correct answer: The project completion date moves three days later. An activity on the critical path has zero float, so a delay pushes the project completion date later by the same amount unless corrective action is taken.
- A non-critical activity automatically absorbs the delay. Non-critical activities do not automatically absorb a delay on the critical path.
- Project duration remains unchanged because float is shared. Float belongs to non-critical activities; the critical path has none to share.
- Only the project budget changes, not its completion date. A delay to a critical activity affects the completion date, not only the budget.