In a project network, an activity on the critical path has zero float and is delayed by three days. If no corrective action is taken, what is the expected effect?

A. The project completion date moves three days later.
B. A non-critical activity automatically absorbs the delay.
C. Project duration remains unchanged because float is shared.
D. Only the project budget changes, not its completion date.
Correct Answer: A. The project completion date moves three days later.

Correct answer: The project completion date moves three days later. An activity on the critical path has zero float, so a delay pushes the project completion date later by the same amount unless corrective action is taken.

  • A non-critical activity automatically absorbs the delay. Non-critical activities do not automatically absorb a delay on the critical path.
  • Project duration remains unchanged because float is shared. Float belongs to non-critical activities; the critical path has none to share.
  • Only the project budget changes, not its completion date. A delay to a critical activity affects the completion date, not only the budget.