Actual price is Rs. 12, standard price is Rs. 10 and 500 units were purchased. The material price variance is:

A. Rs. 1,000 adverse
B. Rs. 1,000 favorable
C. Rs. 5,000 adverse
D. Rs. 600 adverse
Correct Answer: A. Rs. 1,000 adverse

MPV = (AP - SP) x AQ = (12 - 10) x 500 = Rs. 1,000 adverse.