Correct Answer:
A. Direct materials + direct labour + direct expenses
Correct answer: Direct materials + direct labour + direct expenses. Prime cost = direct materials + direct labour + direct expenses.
Background: Prime cost is the direct cost of making a product.
- Indirect materials + indirect labour: Indirect costs are overheads.
- Factory overhead only: Factory overhead is not prime cost.
- Selling and distribution cost: Selling and distribution costs are not prime costs.
Did you know? Adding factory overhead gives the factory cost.
Memory trick: Prime = direct costs.