Four men working together can do a ditch in 42 days. They begin, one man half days. How long will it take to complete

  • A. 45 days
  • B. 48 days
  • C. 52 days
  • D. 60 days
Correct Answer: B. 48 days
Work and time problem using proportion of man-days.